Comment on the agreement on the operation at the interconnection point "Ronneburg"

In accordance with Article 4 of the “COMMISSION REGULATION (EU) 2015/703 of 30 April 2015 establishing a Network Code on Interoperability and Data Exchange Rules”, that describes the information obligations of the Transmission System Operators with regards to the conclusion or the amendment of an interconnection agreement, Network Users are invited to comment on the proposed wording of the following provisions of the agreement on the operation at the interconnection point Ronneburg between GASCADE Gastransport GmbH, Open Grid Europe GmbH and Ferngas Thüringen-Sachsen GmbH (now Ferngas Netzgesellschaft mbH).

(Quote from NC INT Art. 4 (2) for your information:
“Before concluding or amending an interconnection agreement which contains the rules referred to in Article 3(c), (d) and (e), transmission system operators shall invite network users to comment on the proposed text of those rules at least two months before the agreement is concluded or amended. The transmission system operators shall take the network users' comments into account when concluding or amending their interconnection agreement. “)

If your company is interested in using the provided transport capacities in Ronneburg, you are welcome to comment on the attached provisions concerning the matching process, the allocation of gas quantities and the communication procedure in case of exceptional events and send your comments via contact@gascade.de until 25 September 2017.

Annex:
Agreement on the operation at the interconnection point “Ronneburg“ until 1 October 2018, 6 am (excerpt on two pages, German language only)